- · TIME & WORKImportant Facts:1.If A can do a piece of work in n days, then A's 1 day work=1/n2.If A's 1 day's work=1/n, then A can finish the work in n days.Ex: If A can do a piece of work in 4 days,then A's 1 day's work=1/4.If A's 1 day’s work=1/5, then A can finish the work in 5 days3.If A is thrice as good workman as B,then: Ratio of work done byA and B =3:1. Ratio of time taken by A and B to finish a work=1:34.Definition of Variation: The change in two different variablesfollow some definite rule. It said that the two variables varydirectly or inversely.Its notation is X/Y=k, where k is calledconstant. This variation is called direct variation. XY=k. Thisvariation is called inverse variation.5.Some Pairs of Variables:i)Number of workers and their wages. If the number of workersincreases, their total wages increase. If the number of daysreduced, there will be less work. If the number of days isincreased, there will be more work. Therefore, here we havedirect proportion or direct variation.ii)Number workers and days required to do a certain work is anexample of inverse variation. If more men are employed, theywill require fewer days and if there are less number of workers,more days are required.iii)There is an inverse proportion between the daily hours of awork and the days required. If the number of hours is increased,less number of days are required and if the number of hours isreduced, more days are required.6.Some Important Tips:More Men -Less Days and Conversely More Day-Less Men.More Men -More Work and Conversely More Work-More Men.More Days-More Work and Conversely More Work-More Days.Number of days required to complete the given work=Total work/Oneday’s work.Since the total work is assumed to be one(unit), the number of daysrequired to complete the given work would be the reciprocal of oneday’s work.Sometimes, the problems on time and work can be solved using theproportional rule ((man*days*hours)/work) in another situation.7.If men is fixed,work is proportional to time. If work is fixed,then time is inversely proportional to men therefore,(M1*T1/W1)=(M2*T2/W2)Problems1)If 9 men working 6 hours a day can do a work in 88 days. Then 6 menworking 8 hours a day can do it in how many days?Sol: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)so (9*6*88/1)=(6*8*d/1)on solving, d=99 days.2)If 34 men completed 2/5th of a work in 8 days working 9 hours a day.How many more man should be engaged to finish the rest of the work in6 days working 9 hours a day?Sol: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)so, (34*8*9/(2/5))=(x*6*9/(3/5))so x=136 mennumber of men to be added to finish the work=136-34=102 men3)If 5 women or 8 girls can do a work in 84 days. In how many days can10 women and 5 girls can do the same work?Sol: Given that 5 women is equal to 8 girls to complete a workso, 10 women=16 girls.Therefore 10women +5girls=16girls+5girls=21girls.8 girls can do a work in 84 daysthen 21 girls ---------------?answer= (8*84/21)=32days.Therefore 10 women and 5 girls can a work in 32days4)Worker A takes 8 hours to do a job. Worker B takes 10hours to do thesame job. How long it take both A & B, working together but independently,to do the same job?Sol: A's one hour work=1/8.B's one hour work=1/10(A+B)'s one hour work=1/8+1/10 =9/40Both A & B can finish the work in 40/9 days5)A can finish a work in 18 days and B can do the same work in half thetime taken by A. Then, working together, what part of the same work theycan finish in a day?Sol: Given that B alone can complete the same work in days=half the timetaken by A=9daysA's one day work=1/18B's one day work=1/9(A+B)'s one day work=1/18+1/9=1/66)A is twice as good a workman as B and together they finish a piece ofwork in 18 days.In how many days will A alone finish the work.Sol: if A takes x days to do a work thenB takes 2x days to do the same work=>1/x+1/2x=1/18=>3/2x=1/18=>x=27 days.Hence, A alone can finish the work in 27 days.7)A can do a certain work in 12 days. B is 60% more efficient than A. Howmany days does B alone take to do the same job?Sol: Ratio of time taken by A&B=160:100 =8:5Suppose B alone takes x days to do the job.Then, 8:5::12:x=> 8x=5*12=> x=15/2 days.8)A can do a piece of work n 7 days of 9 hours each and B alone can do itin 6 days of 7 hours each. How long will they take to do it working together8 2/5 hours a day?Sol: A can complete the work in (7*9)=63 daysB can complete the work in (6*7)=42 days=> A's one hour's work=1/63 andB's one hour work=1/42(A+B)'s one hour work=1/63+1/42=5/126Therefore, Both can finish the work in 126/5 hours.Number of days of 8 2/5 hours each=(126*5/(5*42))=3days9)A takes twice as much time as B or thrice as much time to finish a pieceof work. Working together they can finish the work in 2 days. B can do thework alone in ?Sol: Suppose A,B and C take x,x/2 and x/3 hours respectively finish thework then 1/x+2/x+3/x=1/2=> 6/x=1/2=>x=12So, B takes 6 hours to finish the work.10)X can do ¼ of a work in 10 days, Y can do 40% of work in 40 days and Zcan do 1/3 of work in 13 days. Who will complete the work first?Sol: Whole work will be done by X in 10*4=40 days.Whole work will be done by Y in (40*100/40)=100 days.Whole work will be done by Z in (13*3)=39 daysTherefore,Z will complete the work first.Complex Problems1)A and B undertake to do a piece of workfor Rs 600.A alone can do it in6 days while B alone can do it in 8 days. With the help of C, they can finishit in 3 days, Find the share of each?\Sol: C's one day's work=(1/3)-(1/6+1/8)=1/24Therefore, A:B:C= Ratio of their one day’s work=1/6:1/8:1/24=4:3:1A's share=Rs (600*4/8)=300B's share= Rs (600*3/8)=225C's share=Rs[600-(300+225)]=Rs 752)A can do a piece of work in 80 days. He works at it for 10 days & then B alone finishes the remaining work in 42 days. In how much time will A and B, working together, finish the work?Sol: Work done by A in 10 days=10/80=1/8Remaining work=(1-(1/8))=7/8Now, work will be done by B in 42 days.Whole work will be done by B in (42*8/7)=48 daysTherefore, A's one day's work=1/80B’s one day's work=1/48(A+B)'s one day's work=1/80+1/48=8/240=1/30Hence, both will finish the work in 30 days.3)P,Q and R are three typists who working simultaneously can type 216 pagesin 4 hours In one hour , R can type as many pages more than Q as Q can type morethan P. During a period of five hours, R can type as many pages as P canduring seven hours. How many pages does each of them type per hour?Sol:Let the number of pages typed in one hour by P, Q and R be x,y and zrespectivelyThen x+y+z=216/4=54 ---------------1z-y=y-x => 2y=x+z -----------25z=7x => x=5x/7 ---------------3Solving 1,2 and 3 we get x=15,y=18, and z=214)Ronald and Elan are working on an assignment. Ronald takes 6 hours totype 32 pages on a computer, while Elan takes 5 hours to type 40 pages.How much time will they take, working together on two different computersto type an assignment of 110 pages?Sol: Number of pages typed by Ronald in one hour=32/6=16/3Number of pages typed by Elan in one hour=40/5=8Number of pages typed by both in one hour=((16/3)+8)=40/3Time taken by both to type 110 pages=110*3/40=8 hours.5)Two workers A and B are engaged to do a work. A working alone takes 8 hoursmore to complete the job than if both working together. If B worked alone,he would need 4 1/2 hours more to compete the job than they both workingtogether. What time would they take to do the work together.Sol: (1/(x+8))+(1/(x+(9/2)))=1/x=>(1/(x+8))+(2/(2x+9))=1/x=> x(4x+25)=(x+8)(2x+9)=> 2x2 =72=> x2 = 36=> x=6Therefore, A and B together can do the work in 6 days.6)A and B can do a work in12 days, B and C in 15 days, C and A in 20 days.If A,B and C work together, they will complete the work in how many days?Sol: (A+B)'s one day's work=1/12;(B+C)'s one day's work=1/15;(A+C)'s one day's work=1/20;Adding we get 2(A+B+C)'s one day's work=1/12+1/15+1/20=12/60=1/5(A+B+C)'s one day work=1/10So, A,B,and C together can complete the work in 10 days.7)A and B can do a work in 8 days, B and C can do the same wor in 12 days.A,B and C together can finish it in 6 days. A and C together will do it inhow many days?Sol: (A+B+C)'s one day's work=1/6;(A+B)'s one day's work=1/8;(B+C)'s one day's work=1/12;(A+C)'s one day's work=2(A+B+C)'s one day's work-((A+B)'s one daywork+(B+C)'s one day work)= (2/6)-(1/8+1/12)=(1/3)- (5/24)=3/24=1/8So, A and C together will do the work in 8 days.8)A can do a certain work in the same time in which B and C together can do it.If A and B together could do it in 10 days and C alone in 50 days, then B alonecould do it in how many days?Sol: (A+B)'s one day's work=1/10;C's one day's work=1/50(A+B+C)'s one day's work=(1/10+1/50)=6/50=3/25Also, A's one day's work=(B+C)’s one day's workFrom i and ii ,we get :2*(A's one day's work)=3/25=> A's one day's work=3/50B's one day’s work=(1/10-3/50)=2/50=1/25B alone could complete the work in 25 days.9) A is thrice as good a workman as B and therefore is able to finish a jobin 60 days less than B. Working together, they can do it in:Sol: Ratio of times taken by A and B=1:3.If difference of time is 2 days , B takes 3 daysIf difference of time is 60 days, B takes (3*60/2)=90 daysSo, A takes 30 days to do the work=1/90A's one day's work=1/30;B's one day's work=1/90;(A+B)'s one day's work=1/30+1/90=4/90=2/45Therefore, A&B together can do the work in 45/2days10) A can do a piece of work in 80 days. He works at it for 10 days and thenB alone finishes the remaining work in 42 days. In how much time will A&B,working together, finish the work?Sol: Work Done by A n 10 days =10/80=1/8Remaining work =1-1/8=7/8Now 7/8 work is done by B in 42 daysWhole work will be done by B in 42*8/7= 48 days=> A's one day's work =1/80 andB's one day's work =1/48(A+B)'s one day's work = 1/80+1/48 = 8/240 = 1/30Hence both will finish the work in 30 days.11) 45 men can complete a work in 16 days. Six days after they started working,so more men joined them. How many days will they now take to complete theremaining work?Sol: M1*D1/W1=M2*D2/W2=>45*6/(6/16)=75*x/(1-(6/16))=> x=6 days12)A is 50% as efficient as B. C does half the work done by A&B together. IfC alone does the work n 40 days, then A,B and C together can do the work in:Sol: A's one day's work:B's one days work=150:100 =3:2Let A's &B's one day's work be 3x and 2x days respectively.Then C's one day's work=5x/2=> 5x/2=1/40=> x=((1/40)*(2/5))=1/100A's one day's work=3/100B's one day's work=1/50C's one day's work=1/40So, A,B and C can do the work in 13 1/3 days.13)A can finish a work in 18 days and B can do the same work in 15 days. Bworked for 10 days and left the job. In how many days A alone can finish theremaining work?Sol: B's 10 day's work=10/15=2/3Remaining work=(1-(2/3))=1/3Now, 1/18 work is done by A in 1 day.Therefore 1/3 work is done by A in 18*(1/3)=6 days.14)A can finish a work in 24 days, B n 9 days and C in 12 days. B&C start thework but are forced to leave after 3 days. The remaining work done by A in:Sol: (B+C)'s one day's work=1/9+1/12=7/36Work done by B & C in 3 days=3*7/36=7/12Remaining work=1-(7/12)=5/12Now , 1/24 work is done by A in 1 day.So, 5/12 work is done by A in 24*5/12=10 days15)X and Y can do a piece of work n 20 days and 12 days respectively. X startedthe work alone and then after 4 days Y joined him till the completion of work.How long did the work last?Sol: work done by X in 4 days =4/20 =1/5Remaining work= 1-1/5 =4/5(X+Y)'s one day's work =1/20+1/12 =8/60=2/15Now, 2/15 work is done by X and Y in one day.So, 4/5 work will be done by X and Y in 15/2*4/5=6 daysHence Total time taken =(6+4) days = 10 days16)A does 4/5 of work in 20 days. He then calls in B and they together finishthe remaining work in 3 days. How long B alone would take to do the whole work?Sol: Whole work is done by A in 20*5/4=25 daysNow, (1-(4/5)) i.e 1/5 work is done by A& B in days.Whole work will be done by A& B in 3*5=15 days=>B's one day's work= 1/15-1/25=4/150=2/75So, B alone would do the work in 75/2= 37 ½ days.17) A and B can do a piece of work in 45 days and 40 days respectively. Theybegan to do the work together but A leaves after some days and then B completedthe remaining work n 23 days. The number of days after which A left the work wasSol: (A+B)'s one day's work=1/45+1/40=17/360Work done by B in 23 days=23/40Remaining work=1-(23/40)=17/40Now, 17/360 work was done by (A+B) in 1 day.17/40 work was done by (A+B) in (1*(360/17)*(17/40))= 9 daysSo, A left after 9 days.18)A can do a piece of work in 10 days, B in 15 days. They work for 5 days.The rest of work finished by C in 2 days. If they get Rs 1500 for the wholework, the daily wages of B and C areSol: Part of work done by A= 5/10=1/2Part of work done by B=1/3Part of work done by C=(1-(1/2+1/3))=1/6A's share: B's share: C's share=1/2:1/3:1/6= 3:2:1A's share=(3/6)*1500=750B's share=(2/6)*1500=500C's share=(1/6)*1500=250A's daily wages=750/5=150/-B's daily wages=500/5=100/-C's daily wages=250/2=125/-Daily wages of B&C = 100+125=225/-19)A alone can complete a work in 16 days and B alone can complete the samein 12 days. Starting with A, they work on alternate days. The total work willbe completed in how many days?(a) 12 days (b) 13 days (c) 13 5/7 days (d)13 ¾ daysSol: (A+B)'s 2 days work = 1/16 + 1/12 =7/48work done in 6 pairs of days =(7/48) * 6 = 7/8remaining work = 1- 7/8 = 1/8work done by A on 13th day = 1/16remaining work = 1/8 – 1/16 = 1/16on 14th day, it is B’s turn1/12 work is done by B in 1 day.1/16 work is done by B in ¾ day.Total time taken= 13 ¾ days.So, Answer is: DTop20)A,B and C can do a piece of work in 20,30 and 60 days respectively. In howmany days can A do the work if he is assisted by B and C on every third day?Sol: A's two day's work=2/20=1/10(A+B+C)'s one day's work=1/20+1/30+1/60=6/60=1/10Work done in 3 days=(1/10+1/10)=1/5Now, 1/5 work is done in 3 daysTherefore, Whole work will be done in (3*5)=15 days.21)Seven men can complete a work in 12 days. They started the work and after5 days, two men left. In how many days will the work be completed by theremaining men?(A) 5 (B) 6 (C ) 7 (D) 8 (E) noneSol: 7*12 men complete the work in 1 day.Therefore, 1 man's 1 day's work=1/847 men's 5 days work = 5/12=>remaining work = 1-5/12 = 7/125 men's 1 day's work = 5/845/84 work is don by them in 1 day7/12 work is done by them in ((84/5) * (7/12)) = 49/5 days = 9 4/5 days.Ans: E22).12 men complete a work in 9 days. After they have worked for 6 days, 6 more men joined them. How many days will they take to complete the remaining work?(a) 2 days (b) 3 days (c) 4 days (d) 5daysSol : 1 man's 1 day work = 1/10812 men's 6 days work = 6/9 = 2/3remaining work = 1 – 2/3 = 1/318 men's 1 days work = 18/108 = 1/61/6 work is done by them in 1 daytherefore, 1/3 work is done by them in 6/3 = 2 days.Ans : A23).A man, a woman and a boy can complete a job in 3,4 and 12 days respectively.How many boys must assist 1 man and 1 woman to complete the job in ¼ of a day?(a). 1 (b). 4 (c). 19 (d). 41Sol : (1 man + 1 woman)'s 1 days work = 1/3+1/4=7/12Work done by 1 man and 1 women n 1/4 day=((7/12)*(1/4))=7/48Remaining work= 1- 7/48= 41/48Work done by 1 boy in ¼ day= ((1/12)*(1/4)) =1/48Therefore, Number of boys required= ((41/48)*48)= 41 daysSo,Answer: D24)12 men can complete a piece of work in 4 days, while 15 women can completethe same work in 4 days. 6 men start working on the job and after working for2 days, all of them stopped working. How many women should be put on the jobto complete the remaining work, if it is to be completed in 3 days.(A) 15 (B) 18 (C) 22 (D) data inadequateSol: one man's one day's work= 1/48one woman's one day's work=1/606 men's 2 day's work=((6/48)*2)= ¼Remaining work=3/4Now, 1/60 work s done in 1 day by 1 woman.So, ¾ work will be done in 3 days by (60*(3/4)*(1/3))= 15 woman.So, Answer: A25)Twelve children take sixteen days to complete a work which can be completedby 8 adults in 12 days. Sixteen adults left and four children joined them. Howmany days will they take to complete the remaining work?(A) 3 (B) 4 ( C) 6 (D) 8Sol: one child's one day work= 1/192;one adult's one day's work= 1/96;work done in 3 days=((1/96)*16*3)= 1/2Remaining work= 1 – ½=1/2(6 adults+ 4 children)'s 1 day's work= 6/96+4/192= 1/121/12 work is done by them in 1 day.½ work is done by them 12*(1/2)= 6 daysSo, Answer= C26)Sixteen men can complete a work in twelve days. Twenty four children cancomplete the same work in 18 days. 12 men and 8 children started working andafter eight days three more children joined them. How many days will they nowtake to complete the remaining work?(A) 2 days (B) 4 days ( C) 6 days (D) 8 daysol: one man's one day's work= 1/192one child's one day's work= 1/432Work done in 8 days=8*(12/192+ 8/432)=8*(1/16+1/54) =35/54Remaining work= 1 -35/54= 19/54(12 men+11 children)'s 1 day's work= 12/192 + 11/432 = 19/216Now, 19/216 work is done by them in 1 day.Therefore, 19/54 work will be done by them in ((216/19)*(19/54))= 4 daysSo,Answer: B27)Twenty-four men can complete a work in 16 days. Thirty- two women cancomplete the same work in twenty-four days. Sixteen men and sixteen womenstarted working and worked for 12 days. How many more men are to be added tocomplete the remaining work in 2 days?(A) 16 men (B) 24 men ( C) 36 men (D) 48 menSol: one man's one day's work= 1/384one woman's one day's work=1/768Work done in 12 days= 12*( 16/384 + 16/768) = 12*(3/48)=3/4Remaining work=1 – ¾=1/4(16 men+16 women)'s two day's work =12*( 16/384+16/768)=2/16=1/8Remaining work = 1/4-1/8 =1/81/384 work is done n 1 day by 1 man.Therefore, 1/8 work will be done in 2 days in 384*(1/8)*(1/2)=24men28)4 men and 6 women can complete a work in 8 days, while 3 men and 7 womencan complete it in 10 days. In how many days will 10 women complete it?(A) 35 days (B) 40 days ( C) 45 days (D) 50 daysSol: Let 1 man's 1 day's work =x days and1 woman's 1 day's work=yThen, 4x+6y=1/8 and 3x+7y=1/10.Solving these two equations, we get: x=11/400 and y= 1/400Therefore, 1 woman's 1 day's work=1/400=> 10 women will complete the work in 40 days.Answer: B29)One man,3 women and 4 boys can do a piece of work in 96hrs, 2 men and 8 boyscan do it in 80 hrs, 2 men & 3 women can do it in 120hr. 5Men & 12 boys can doit in?(A) 39 1/11 hrs (B) 42 7/11 hrs ( C) 43 7/11 days (D) 44hrsSol: Let 1 man's 1 hour's work=x1 woman's 1 hour's work=y1 boy's 1 hour's work=zThen, x+3y+4z=1/96 -----------(1)2x+8z= 1/80 ----------(2)adding (2) & (3) and subtracting (1)3x+4z=1/96 ---------(4)From (2) and (4), we get x=1/480Substituting, we get : y=1/720 and z= 1/960(5 men+ 12 boy)'s 1 hour's work=5/480+12/960 =1/96 + 1/80=11/480Therefore, 5 men and 12 boys can do the work in 480/11 or 43 7/11hours.So,Answer: C
Loading...
Subscribe to:
Post Comments (Atom)
0 comments:
Post a Comment